Sunday, June 4, 2017

Strategic Planning For Power Transformers

With an ageing population of transformers it is important for a Utility to have a well defined replacement strategy which is closely backed by an appropriate condition monitoring strategy. The following is a report that I compiled for 6 power stations, most of which were in their half life. This report was done on 2001 but the salient concepts are still relevant.

This report highlights the long-term strategy to manage the ageing generator transformer fleet within a Power Utility. It first concentrates on establishing an estimated remaining life of the transformers and comparing this to the strategic life of plant plans for the stations. From this, recommendations are given on the management method for the transformers concerned.

The transformers for A and B are in a satisfactory condition. Since these stations have a strategic life up to 2011, these transformers will be able to operate until then. No major refurbishment plans are proposed for these transformers other than the proper maintenance as prescribed by Generation.

The transformers for F and E are presently in the latter stages of their life and have an estimated ±10 years life. The strategic remaining station life for F and E are 47 and 48 years respectively. This remaining age difference is too high for life extension methods to be implemented, thus either rewinds or new transformers are proposed for these stations according to end-of-life of the respective transformers. The timing of these rewinds or replacements are highlighted in section 5.3 and the bar chart for strategic planning for the transformers in appendix 2.

The transformers for D are still relatively new but their insulation has shown signs of significant degradation. Proper oil preservation systems need to be implemented as soon as possible to maintain the proper controlled environment within the transformer to stabilise its ageing process. The strategic station life is up to 2048 with an estimated transformer life of ±18 years. This means that these transformers will also have to be either rewound or replaced around 2019.
 
The C transformers have an average remaining life span of 18 years and the proposed strategic life for the station is up to 2035. With a remaining age difference of 17 years, it would be of advantage to apply life extension methods to these transformers to prolong the life for a few years and then rewind/refurbish these transformers to achieve the remaining life. This would be the most cost-effective program when considering the remaining station life.

The decision for replacement or refurbishment of a transformer is both strategic and financial. Much thought need to be given to the future requirements of the plant before such a task can be carried out.


LIFE ESTIMATION OF TRANSFORMERS

Lifetime evaluation of any equipment is related to its ageing process. The principle factor influencing ageing and life expectancy is thermal stress. The life duration of the transformer is assumed to be the life duration of the paper insulation. Abnormal events are normally associated with chemical reactions of pyrolysis, oxidation and hydrolysis taking place within the insulation material. These reactions are accelerated by increases in temperature and in the concentration of oxygen and moisture.

Transformer oil is also affected by chemical degradation. Oxidation can cause acid compounds and sludge to form causing a reduction in dielectric strength and impairing cooling.

There has been a trend evident for large GSU transformers to begin to fail after 18-20 years in service. This trend is evident in many areas of the world and is not simply due to the thermal ageing of the insulation, but due to the effects of system events that accelerate ageing with a consequent reduction in the electrical and mechanical strength of the windings.

According to the OEM, the expected life of transformers is considered to be ± 35 years. This will be used as a basis of end-of-life of the transformers. From the table 1, the proposed remaining life is assumed according to this criterion.

Table 1

Expected Insulation Life – Using Furanic Method
(Extract from Guideline for the extension of substations, research project by EPRI)
One of the most dependable and reproducible measures of paper ageing is the degree of polymerisation (DP) of the cellulose. Cellulose is the principle constituent of insulating papers used in power transformers and the cellulose molecule is made up of a long chain of glucose rings. The DP is the average number of these rings in the molecule. When paper is new the DP is typically between 1000 and 1400, but as the paper ages thermally, the bonds between rings begin to break and the average length of the chain is reduced. The shortening of the chains is also associated with diminished mechanical properties (tensile strength, burst strength, elongation to rupture). A DP value of 200 is generally felt to represent the level, at which “useful mechanical properties” of the paper are lost, so this may be used as an insulation life end-point.

Once a DP value has been determined, a translation is required to establish the relative age of the insulation. The reduction of DP with ageing time does not follow a linear pattern. It is very rapid at first and then becomes more gradual. Shroff and Stannett observed that if any set of ageing data is plotted with DP on a logarithmic scale and time on linear scale straight-line results for the portion of the data after the initial rapid drop-off are obtained. The zero time intercepts for the straight lines range from DP = 700 to 900 for sets of test data at different temperatures and by various investigators. All of the data can be grouped by normalising it based on the time required for DP to reduce to 200 (the life end-point). The resultant graph is shown in figure 1. 

Figure 1



























This is admittedly an approximate method for assessing the condition of the transformer insulation, but it produces an answer that should be of adequate quality to make engineering judgements. For example a transformer with insulation DP = 300 would not be a good candidate for a partial rewind because about 70% of the insulation life has already been consumed.
The following Table 2 illustrates the application of this criterion on the transformers to determine the approximated insulation life. The average curve with DP = 800 at 0 normalised life was used to estimate the normalised life.
The value for C GSU trfr 4 has been estimated to 20 years remaining insulation life due 1994 refurbishment of this transformer after it had failed thus not giving true DP results.

Table 2


























Table 3 




























CONDITION ASSESSMENT

When determining the probability of trouble free service for so many additional years it would be unwise to base the evaluation only on thermal ageing. The decision should be made in terms of different service record aspects as investigated below:


The most widely used screening technique is by Dissolved gas analysis, with Carbon monoxide and Carbon dioxide being the key gases to evaluate. Experience has demonstrated that under normal operating temperatures, the rate of evolution of carbon dioxide typically is 7-20 times higher than that for carbon monoxide, but ratios down to five may be considered normal.

The ANSI/IEEE C57.104, Guide for the Interpretation of gases generated in power transformers gives the following method. Absolute dissolved gas levels are provided for four status conditions ranging from normal operation to modest concern (investigate) to major concern and finally to imminent risk of failure. The CO2 and CO levels (PPM) for each status are as follows:

Table 4

An unusually low CO2/CO ratio with small amounts of gas present could be indicative of a developing problem that could be corrected.

The following is a table of the CO2 and CO results for the GSU transformers. It is an average of the results over the past 5 years to give a realistic distribution of results


Table 5






















From table 5 the transformers that were most affected by insulation breakdown are; E GSU transformers 4 and 3, F GSU transformers 1 and 2, C GSU transformer 1 and D GSU transformers 1 and 2. The reasons could be that of thermal degradation or high oxygen and moisture levels.

Although a transformer might have been designed and tested to withstand mechanical stress resulting from external faults, the latter must nevertheless be considered as an ageing factor. The clamping force of many transformers will be reduced over time due to the insulating material shrinking by means of being compacted by continuous vibrations.

These results are based on historical data which are not available for estimation. It is however assumed that the number and effects, of the short circuit conditions for the transformers are of average quantity and level. That of major events have been recorded as such under thermal effects and insulation breakdown.

Repeated surges will usually not have a cumulative damaging effect on the insulation. However, in the presence of moisture or contamination deposits, repeated surges or over voltages may cause permanent damage in highly stressed areas of the insulation structure or ignite partial discharges that will persist under service voltage.

The basic approach to condition assessment is to use the oil as the primary indicator of the internal condition of the transformer. This assessment is accomplished as follows:

Insulation life is a function of thermal ageing of the system. It is reasonable to expect that the transformer insulation systems will last the expected 30-40 years at full load if the system is maintained in a good condition. Failure or end of life occurs as the result of a variety of mechanisms including poor oil preservation systems. Thus, it is necessary to examine the causes of deterioration of the paper and oil properties.

Insulation can degrade from the exposure to high levels of oxygen and water at normal operating temperatures. This degradation can occur in older transformers having oil expansion tanks with no rubber bags to prevent oxygen from entering the tank or failure to maintain the dehydrating breathers so that water also enters the oil through the expansion tank.
As part of the life extension of transformers, EPRI recommends that the levels of O2 be controlled to a maximum of 2000 PPM.

Table 6 below shows the levels of O2 of the GSU transformers as an average over the past 5 years and indicates that all the GSU transformers are above the EPRI recommended limit of 2000 PPM for oxyGSU This indicates that the existing free breathing system is not adequate to prevent a controlled oxygen environment within the transformer. This further emphasises the importance of the installation of a conservator bag. Of concern are the transformers of D and C since these transformers will have to remain in service for the longest after a decision is taken for replacement/refurbishment. Proper oil preservation systems need to be investigated for these transformers. 

Table 6
The EPRI recommended maximum limit being 2000 PPM
















  



The ageing process is minimal if the oil and paper are kept dry, the oxygen content is nominal, and the hot-spot temperatures are not above standard allowances. If the transformer temperature does not exceed the rating of the paper, it is possible to load the transformer at or above its rating depending on the ambient without significant loss of life.  Failure can result from thermal ageing if the transformer is overloaded to the extent that the hot-spot temperatures above the rating of the paper exists for long periods of time.
transformers are run to full load and all transformers are kept within the specified temperature limits. The transformers for F have shown signs of operating at temperatures higher than the rest of the transformers but these levels have being within the upper limit of 90° C above which the life of the insulation could be drastically affected.

It has been recognised that every internal inspection or relocation of the transformer involves a risk of mechanical damage. Experience indicates that a transformer that has been trouble free so far is more likely to remain so than one that has required on-site repair or needed to be relocated.
Of concern would be that of C GSU transformer 4 where it has experienced a failure in the past resulting in it being repaired and moved.

The above condition assessment establishes that the transformers have been maintained in a satisfactory condition from the resources and technology that was available. It however also points out the effects of oxygen on the insulation life and the level of oxygen within the transformers. When compared to world standards and recommendations these levels are too high. It is worthwhile investigating and implementing methods of control of the levels of oxygen within the transformer. These include the installation of conservator bags within the expansion tank of the transformer.

POSSIBLE SOLUTIONS/ACTION PLAN


The bar chart in Appendix 2 clearly illustrates the long-term plant strategy and the role the GSU transformers would have to play. From the table 7 below the remaining life of the power stations after the operating life of the existing GSU transformers has been exceeded are summarised. This indicates that B and A power stations would not require further planning for transformers since they will outlive the station operating life requirement. For D, F and E replacement/refurbishment strategies will definitely have to be planned. For C, life extension methods/refurbishments could be investigated to try to prolong the life of the existing transformers to last the full life of the station. These will be discussed further.

Table 7
























The transformer life is shortened by a number of events. Taking action to prevent failure from any of these causes is a method for extending life. Controlling the characteristics of the internal transformer system such as controlling the oxygen and water contents will ensure that the maximum designed life is attained. A combination of maintaining the insulation in a good condition with proper loading of the transformers will ensure longer expected life of the transformers. These will be discussed below.

The figure 2 below illustrates the action plan needed to reduce oxygen and moisture levels in the transformer. This is recommended by EPRI in the guideline for the life extension of substations:

Figure 2



































EPRI recommends that the oxygen content of the oil be controlled to a maximum of 2000 PPM. As illustrated in section 4.4, the GSU transformers have a high exposure to oxygen and have been this way since initial installation. Thus, methods of control will have to be implemented to reduce the levels of oxygen. One of these methods is the installation of a transformer bag in the conservator tank. This project has already been investigated and is being implement for D. Investigations will have to be carried out for the other stations. Based on the life of plant strategy, the installation of bags for F and E will have to be investigated under the refurbishment/replacement plans for the transformers. Since life extension plans will have to be investigated/implemented for C, the transformer conservator bags will also be highly recommended in this case. 


To prolong to lives of the existing transformers it is of extreme importance to have timely and high quality maintenance. In the long term, as a minimum, the following points should be noted:

·   Oil pumps are to be replaced with refurbished pumps or new pumps having improved bearings.
·    The tap changer must be regularly serviced and inspected. Parts that are worn and parts that have a history of problems are to be replaced. Internal leads are to be inspected and the tape replaced if needed.
·  Bushings are to be timeously tested for power factor. If a high value is reached, replacement will have to be investigated.
·   Inspect and test control and protective devices. If signs of deterioration and imminent failure are evident, these need to be replaced. The control wiring is to be replaced if it shows signs of severe deterioration.
·   The oil properties including dielectric, power factor and water content are to be checked. If the properties are out of line, the oil must be passed through processing equipment where the oil is filtered, dehumidified and degassed.
·    Repair or replace gaskets that are leaking.

The proper maintenance and testing of the transformers need to be carried out according to IEEE and standards.


The condition of the various transformer system components must be carefully considered when making decisions on major repair or replacement of transformers. Careful considerations should be given to expectations for major repairs that are to be performed by a repair facility:

1.  What is the expected life after repair? Is the expected life after repairing the same as for a new transformer? Is it the expected original life minus the service up to the time of repair? It is not realistic to expect the same total life after repair as for a new transformer.

2. The condition of the paper insulation is of obvious importance when making repair decisions. If all indicators are positive (O2 and H2O have been low, CO and CO2 are low, the transformer has been maintained in a good condition, there has not been excessive overloading, and the furans are low ) the probability is that the condition of the insulation is good and that repair is appropriate from this viewpoint.

3. If the indicators are questionable or negative, it is recommended that a sample of insulation be removed for degree of polymerisation (DP) tests. The following guidelines based on DP analysis can be used:

DP < 200                The paper is near the end of its useful life and repair of such windings is not recommended.
400 < DP < 600         Reuse of the coils is questionable unless the repair is to see  limited service.
DP > 600                     Some life has been removed but most of the useful life remains so that reuse of the coils is usually satisfactory.

4. The degree of refurbishment justified depends upon the age and condition of the transformer. The options are:


  • To rewind the transformer,
  • To rewind with replacement of bushings and tap changer,
  • To a redesign using modern techniques to adapt the existing core and tank and bring the
  • refurbished transformer up to the modern standards of a new transformer.  




The long-term plant strategy for transformers (Appendix 2) puts C in a unique situation. There is a possibility to prolong the life of the transformer but this may not be enough to last the end-of-life of the station. It may not be cost effective to replace the transformers since the remaining life of the station would not be enough to get a return on investment. Since refurbishment/rewind only offers limited life when compared to that of a new transformer (due to the ageing of the magnetic circuit and materials of the remaining parts) it may be an option to be investigated when the capability of the existing components (insulation, tap changer, bushings) of the transformers have been exhausted.


The refurbishment/replacement of transformers is suggested for D, F and E. This decision is based on the station long-term plant strategy and the condition of the transformers. The long term plant strategy for transformers (appendix 2) illustrates the timing of such a replacement plan. This refurbishment/replacement program is capital intensive and must be included in the long term plant budgeting.

The spare transformers within also plays an important role. One spare transformer exist for A and B. One spare transformer exist for F. For E a spare set of windings is available in the stores.

The spare transformer for F plays a very important role in that it can be assembled and made ready for a swap during one of the routine outages and the existing one be rewound/refurbished or replaced. This can then replace the GSU transformer of the other unit.

The spare set of windings for E can be used as a model for the manufacture of further windings. These can be manufactured now while the existing transformers are still in operation. This will reduce the down time when these transformers are rewound. 

CONCLUSION

The average remaining life of the transformer has been estimated using the design age and the estimated insulation life (illustrated in Table 3). This gives a realistic estimated life that can be used for the future strategic planning of the transformers within the Utility.

The condition assessment tries to establish the present condition of the transformers and how it was maintained in the past. It helps to identify deficiencies in the method of maintenance and areas in which concentration needs to be given to prolong the life of the transformers. From this, it has been established that the transformers have a high concentration of oxygen, which is the main factor in the deterioration of the paper insulation. This is due to the fact that there were no conservator bags installed from initial installation. From a financial and strategic basis, it is suggested that conservator bags be installed in the transformers at D. It is also highly recommended that conservator bags be installed at C since it is of utmost importance in the long term to prolong the life of these transformers, since only a refurbishment will eventually be needed instead of a replacement.

It is beneficial to prolong the life of existing equipment for as long as possible before the option of replacement is visited, however the replacement should be planned adequately to ensure continuous operation of the plant. This will also hold true for the GSU transformers within Utility. As far as possible the maintenance and operating characteristics of the transformers must be within proper standards and limits respectively. 

The strategic plan for the GSU transformers may be found in the bar chart in appendix 2. This highlights that the transformers at A and B don’t need to be replaced or refurbished since they will outlive the station life if proper maintenance is carried out on these transformers.

It is suggested that the F spare transformer be refurbished and replace GSU transformer 1. Thereafter refurbishing/replacing GSU transformer 1 and replacing GSU transformer 2 with this.

Further investigations will have to be made into using the spare windings available for E in pre-manufacturing windings for a rewind, thus reducing the down time of refurbishment. 

The D GSU transformers must be refurbished around 2017. Life extension plans need to be implemented at C as soon as possible and refurbishment’s around 2015.

This gives an estimated guide for the long term planning and timing of events for the GSU transformers within the Utility. The condition of these transformers must however be continually monitored and evaluated since any adverse events could affect the above estimation and this needs to be properly analysed and managed. 


RECOMMENDATIONS


  1. Install conservator bags in the GSUs transformers at D (March 2000).
  2. Install conservator bags in the GSUs transformers at C (2001/2).
  3. Carry out the recommended maintenance as per - generation requirements on all GSU transformers.
  4. Refurbish Spare F transformer (2003)
  5. Swap spare F transformer with GSU trfr. 1 at F (2004)
  6. Refurbish/replace F GSU trfr. 1 (2005)
  7. Swap F GSU trfr.2 with GSU trfr. 1 (2006/2007)
  8. Refurbish/replace F GSU Trfr. 2. Keep as spare.
  9. E - Use Spare set of windings to pre-manufacture windings for rewind / replacement (2004)
  10. E - GSU trfr. 4 replace windings/refurbish/replace (2006)
  11. E - GSU trfr. 3 replace/refurbish (2007)
  12. E - GSU trfr. 2 replacement/refurbish (2009)
  13. E - GSU trfr. 1 replacement/refurbish (2010)
  14. C - GSU trfr.1 Refurbish/replace (2015)
  15. C - GSU trfr. 3 refurbish/replace (2016)
  16. C - GSU trfr. 4 refurbish/replace (2017)
  17. C - GSU trfr. 2 refurbish/replace (2018)
  18. D - GSU trfr. 1 refurbish/replace (2017)
  19. D - GSU trfr. 2 refurbish/replace (2018)
  20. A & B - maintain transformer - will last station life   



ABBREVIATIONS

A                      A Power Station
B                      B power Station
C                     C Power Station
CH4                 Methane
C2H2               Acetylene
C2H4               Ethylene
C2H6               Ethane
CO                  Carbon Monoxide
CO2                Carbon dioxide
O2                   Oxygen
D                     D Power Station
DGA                Dissolved Gas Analysis
DP                   Degree of Polymerisation
E                      E Power Station
EPRI               Electric Power Research Institute
F                      F Power Station
GSU Trfr.        GSU Transformer
H2                   Hydrogen
H2O                Water
OEM               Original equipment manufacturer
PPM                Parts per million
TDCG             Total Dissolved Combustible Gas


BIBLIOGRAPHY

  1. Lifetime Evaluation of Transformers, Working group 09 of study committee 12, Electra No. 150 October 1993.
  2. DJ Allan and A White, Life Management of Power Plants, IEE Conference Publication No. 401, 1994
  3. Guidelines for the Life Extension of Substations, TR-105070 Research project 2747-09, EPRI, April 1995.
  4. IEEE Guide for the Interpretation of Gases Generated in Oil-immersed Transformers, IEEE Std C57.104-1991.
  5. IEEE Guide for the Loading Mineral-Oil-Immersed Transformers, IEEE Std C57.91-1995.
  6. Life Extension Program for Older Substation Transformers, Wallace J. Penner, Entergy Services, Inc. Doble Engineering Company, 1994.
  7. Oil Cooled Power Transformer and Reactor Refurbishment, CE Odendaal, ABB Powertech Transformers (Pty) Ltd.

APPENDIX 1















APPENDIX 2



















0 comments:

Post a Comment